Australian construction payment

Security of Payment
across Australia

Find the provisions for one jurisdiction, or compare them side by side.

Australian Security of Payment comparisonUpdated 23 October 2026

Choose your view

8 jurisdictions · 28 comparison topics

Selecting a jurisdiction does not determine which law applies. Check the location and scope of the work, contract dates, exclusions and transitional provisions.

Jurisdiction reference

Queensland

28 of 28 topics · Provisions checked 23 October 2026

01Legislation and application

Legislation

Building Industry Fairness (Security of Payment) Act 2017

Act consolidation date

28 May 2026

Application and key exclusions

Chapter 3 applies to construction contracts, including older contracts, except unfinished claims preserved under the repealed 2004 Act. Domestic building work for a resident owner’s own home is excluded, but owner-builders and building contractors are not resident owners for this exclusion. Financial, employment and non-value-based consideration exclusions also apply (s 61). Giving a subcontractors’ charge notice restricts Chapter 3 remedies (s 62).

Geographical application

Excludes work outside Queensland and related goods and services for that work, regardless of the contract’s chosen law (s 61(1), (4)).

02Counting days

Statutory day terminology

Business days. The 28-day final-claim period uses calendar days (Sch 2; s 75(3)(b)).

Days excluded from the statutory count

Saturdays, Sundays, public, special or bank holidays at the place where the relevant act is to be or may be done, and 22–24 December, 27–31 December and 2–10 January inclusive (Sch 2).

Treatment of part-day public holidays

Christmas Eve is excluded for the whole day by the BIF Act, independently of the public holiday from 6 pm to midnight. No express general whole-day deeming rule for other part-day holidays appears in the BIF Act (Sch 2; Holidays Act 1983 s 2(3)).

03Payment entitlement and valuation

Reference date required

Yes. A contractual reference date applies; if none is stated, the statutory monthly date applies (ss 67, 70).

Entitlement to progress payments

Yes, from each reference date, for work carried out or related goods and services supplied under the contract (s 70).

Frequency of payment claims

No more than one payment claim for each reference date. A claim may repeat an earlier amount (s 75(4)–(5)).

Amount of a progress payment

Calculate the amount under the contract. If the contract does not provide for it, value the work or related goods and services under the statutory valuation rules (ss 71–72).

04Payment claims

Name of the payment claim

Payment claim (ss 68, 75(1)).

Who gives and receives a payment claim

The claimant gives the claim to the person who is or may be liable to make the payment under the contract (the respondent) (s 75(1)).

When a payment claim may first be given

On or after each reference date. If the contract does not provide a reference date, use the last day of the first month of work or supply and each subsequent month (ss 67(1), 70, 75(1)).

Payment claims after termination

If the contract does not provide for a reference date surviving termination, or purports to prevent one, the final reference date is termination. Otherwise the surviving contractual reference date governs (s 67(2)).

Required payment claim content

Be in writing, identify the work or related goods and services, state the claimed amount and request payment. A document bearing “invoice” satisfies the request requirement. The current Regulation prescribes no additional claim information (s 68). See the supporting-statement requirement below.

Must the claim identify the SOP Act

No statutory endorsement is required. The claim must request payment (s 68).

Effect of giving a claim early

No express deeming rule turns an early claim into a timely claim. Entitlement arises from the reference date (ss 67, 70, 75).

Latest time for a payment claim

Interim: before the end of the longer of the contractual claim period and 6 months after the relevant work or supply. Final: before the end of the longest of the contractual period, 28 calendar days after the last defects liability period ends, 6 months after completion of all work, or 6 months after complete supply of related goods and services (s 75(2)–(3)).

Subcontractor payment supporting statement

Required if there is a subcontract under the claimed contract and that contract is not itself a subcontract. Declare all amounts owed at the claim date are paid, or identify each unpaid subcontractor, amount, claim details, work/supply date and reason for non-payment, and confirm all others are paid. Non-compliance is an offence but does not invalidate the claim (s 75(6)–(9)).

05Payment schedules

Name of the response

Payment schedule (ss 69, 76).

Required response content

Be in writing, identify the payment claim and state the amount proposed, including nil. If less than the claimed amount, explain the difference and give reasons for withholding payment. The current Regulation prescribes no additional schedule information (s 69).

Who gives and receives the response

The respondent must give the payment schedule to the claimant unless the claim is paid in full by the due date (s 76(1)–(2)).

Time to give a response

Within the earlier of the contractual schedule period and 15 business days after the payment claim is given. A schedule is mandatory unless the claim is paid in full by the payment due date; failure is an offence (s 76(1)–(2)).

Amount payable and failure to respond

A required payment schedule commits the respondent to its proposed amount by the due date, subject to required retention under Part 4A. Without a required schedule, the claimed amount is payable by the due date. Failure to give a required schedule or pay its amount is an offence (ss 76–78).

06Payment due dates

Payment due date

Use the contractual due date; if none, 10 business days after the payment claim. QBCC Act ss 67U and 67W void terms exceeding 25 business days for construction management trade contracts/subcontracts or 15 business days for commercial building contracts. A contract caught by BIF Act s 73(4) falls back to the 10-business-day rule; the cap is not automatically the replacement due date (s 73).

07Suspension

Right to suspend and prerequisites

For an unpaid amount owed on a claim or an unpaid adjudicated amount, give written notice identifying the Act and wait at least 2 business days. The right continues for 3 business days after payment. A subcontractors’ charge notice can prevent suspension for the same work or supply (ss 62, 78, 92, 98).

Financial effects of lawful suspension

If the respondent removes work or supply because the claimant exercises the statutory suspension right, the respondent must pay the claimant’s resulting loss or expenses. The claimant is not liable to the respondent, or anyone claiming through it, for loss or damage caused by the suspension (s 98(3)–(4)).

Sources and scope

This comparison summarises 28 security of payment topics across Australia’s eight states and territories. The provisions were reviewed on the dates shown for each jurisdiction in October 2026. Act consolidation dates are listed separately. Case-law commentary is not included.

The comparison is a concise reference to selected provisions, not a complete account of the legislation or adjudication process. Check the current Act, any applicable regulations and the contract before acting. Contract dates, transitional provisions, exclusions and the circumstances of the work can affect which requirements apply.

General information only, not legal, contractual or professional advice. Obtain project-specific advice before issuing or responding to a claim, calculating a deadline or suspending work. Legislation may have changed since the review dates shown.